CAMS and Fire Alarm System and Sprinklers Replacement(C40853)- MTA C&D
Central Alarm Monitoring System – C40853 is a MTA migration project to migrate current Fire alarm network from MTA Enterprise Network to MTA EMD Network and migrate the data from legacy central alarm management servers to new CAMS servers at core headend, RCC and BRCC.
- ProInfratek is working with the MTA to set up network equipment at RCC, BRCC Data centers in New York City, and three other satellite locations to facilitate data migration from legacy central alarm management servers to new servers, as well as Network migration from MTA Enterprise Network to MTA EMD Network.
- There are analog p Responsible to design, configure, test and commission network switches to terminate CAMS ,servers and other end devices hones that will be installed as a part of the telephone ramp up in one of the communication rooms.
- ProInfratek is responsible for Network Configuration in 3 head end locations (RCC, BRCC and 2 Broadway, MTA Headquarters) and to connect with the existing network.
- Connecting CAMS workstation to the existing network is also taken care of.
- Responsible for surveying 18 substations and 2 maintenance facilities and providing available port for connecting new FACP panel to the access node.